Dependency like "Finish to Start" or "Start to Finish"

The dependency mapping could be more robust like MS Project where we could drag one parent dependency items end date to impact the child dependent start date to move. It's a feature implemented in MS Project for a very long time and is truly useful when you are tracking someones work to start yours , Start to finish , finish to Finish , start to start and finish to start could be really useful dependency tracker for Aha!   

  • ADMIN RESPONSE
    Feb 28, 2020

    Thank you for your idea. Dependencies in Aha! are currently "finish to start." Dependent bars can be moved simultaneously on the Gantt by multi-selecting and dragging together.

  • Attach files
  • Guest
    Reply
    |
    Apr 28, 2020

    In agile/iterative product management, tracking finish-to-finish relationships is critical for me. It matters less for me that something starts after something else ends than it does that one thing can't truly be done until something else is done--when they start is somewhat arbitrary.

  • Guest
    Reply
    |
    Aug 7, 2019

    Looking forward to understand how the moving a feature also moved another feature on gnatt.