Created by Dale Potter
Created on Oct 24, 2023

Dependency roadmap as a standard view

Who would benefit?

Users that:

  • need to track upstream work they are dependent on

  • need to understand downstream work that is dependent on their work

  • need to easily identify delivery risks based on dependencies

What impact would it make?

A roadmap is a great visual for understanding the relationship between two pieces of work.

How should it work?

In a nutshell:

  • A Gantt can show two dependent work items linked by an arrow, but with large volumes, this can become difficult to interpret.

  • The proposed design uses a custom roadmap format to show the downstream work in a column (with columns for any other related data), and the upstream work on the roadmap bars (with any other related data).

  • A calculated column is used to compare the start date of the downstream work with the due date of the upstream work (identify if work item A is planned to complete after the start date of work item B). Problematic dependencies are highlighted in red, while others are green.


  • ADMIN RESPONSE
    Nov 9, 2023

    A new article has been added to our knowledge base to help you build out this view. Let us know what you think!