Mapping dependencies

That we can only have End-to-Start Dependencies drawn is causing issues with our program Overviews. Our Managers are concerned by all of the red. Please enable us to also include Start-to-Start Dependencies, and Start-to-End Dependencies.


If we can't have this functionality, we may be asked to revert back to another planning tool that will require manual effort outside of Aha. Not what we Program Managers want at all.


  • Attach files
  • Guest
    Reply
    |
    Apr 18, 2023

    Hi, we hade the same issue yesterday when discussing GANTT charts. One team member asked for the function "finish-to-finish" and referred to MS Project. But that seems not to be possible in Aha!, at least right now.

  • Kristy Tupper
    Reply
    |
    Nov 29, 2022

    Totally agree with Gianmarco. At the very least, finish-finish is required for accurate program management.

  • Gianmarco Spiga
    Reply
    |
    May 5, 2022

    Second this! Finish-Finish dependencies at least would help lots. Work is often done concurrently and not sequentially.