That we can only have End-to-Start Dependencies drawn is causing issues with our program Overviews. Our Managers are concerned by all of the red. Please enable us to also include Start-to-Start Dependencies, and Start-to-End Dependencies.
If we can't have this functionality, we may be asked to revert back to another planning tool that will require manual effort outside of Aha. Not what we Program Managers want at all.
The issue has been raised by our users. Especially around having to explain the red dependency lines. What can be done to expediate this idea. It was submitted over 2 years ago.
Hi, we hade the same issue yesterday when discussing GANTT charts. One team member asked for the function "finish-to-finish" and referred to MS Project. But that seems not to be possible in Aha!, at least right now.
Totally agree with Gianmarco. At the very least, finish-finish is required for accurate program management.
Second this! Finish-Finish dependencies at least would help lots. Work is often done concurrently and not sequentially.