Skip to Main Content
Status Shipped
Categories Releases
Created by Guest
Created on May 12, 2014

Capacity tracking for assignees

I have resources (assignees) that are assigned to features across multiple products and product lines.  I'd like the capacity planning functionality to be able to track when I've over-committed them

  • ADMIN RESPONSE
    Nov 12, 2019

    You can now quickly visualize each teammate’s workload with the new capacity report.

  • Attach files
  • Michael Loos
    Reply
    |
    Oct 5, 2017

    Could you indicate when this feature will be available in Aha as it is set to planned? We are looking to solve our capacity planning issue and if anyhow possible I would like to do it in Aha using it already in daily business. In this case I would also enrole it to a wide range of people beyond the core product team. Thx!

  • Guest
    Reply
    |
    Aug 12, 2016

    We plan for teams and it would help to be able to see capacity by team. An alternative which might work for all the scenarios mentioned here is to have the capacity bar on top reflect the aggregate sum of planned for the view when filters are selected. Next step might be to have an intuitive way to reflect different capacities and planned amounts by team/resource/tag/...

  • Tom Andries
    Reply
    |
    Sep 20, 2015

    This is indeed a consequence of detailed capacity planning. If I can't see under/overcommitted resources, it's worthless. Another nice feature would be a graph showing the number of items (features/tasks/ ... ) assigned per worker (can't remember in which tool I saw this, but it does help in planning business continuity and knowledge sharing)

  • Guest
    Reply
    |
    Jan 28, 2015

    Would this allow the ability to indicate how much of the estimated time, per feature and requirement, a resource is required for?