Milestones do not currently have a status associated with them. They are just there. This works great for future dates, but when the date passes there is no way to know if the milestone is complete or has been met. It would be great if there was a...
Gary Goz
almost 4 years ago
in Releases
2
Future consideration
I want the external release date to match the internal release date but still round to a time period such as quarters.
Right now if you set the external release date to be the same as the internal release date then the external date moves with the internal date. I would like an option that when you are rounding an external date that it can also update the date to ...
Guest
over 7 years ago
in Releases / Roadmaps
3
Future consideration
Ability to show more release details on the feature board
In the feature board view, the top of each release column shows very limited information today. Just release name, release date, and capacity. It would be useful to show more information about a particular release at the top of each release column...
Andrew Foster
almost 2 years ago
in Releases
1
Future consideration
Notify Roadmap Stakeholders if an upcoming release is over/underplanned
What is the challenge? In our company, many stakeholders steer the contents of our product roadmap. It would be great if those stakeholders could be automatically informed if an upcoming release is over/underplanned. What is the impact? Better pla...
Need the ability to add To-Do's to a Release Template
I need the ability to add ToDo's to a Release Template. Currently I am able to add ToDo's to a Release Template, but only as part of a Phase/Milestone within a Release Template. This is less than ideal as these ToDo's are quite buried and overlook...
Joe Carpenter
about 5 years ago
in Releases
0
Future consideration
Copy/ Share a Release Template between Product Line
I created a detailed release template at the product line level, and I would like to share that with other product lines and other products. I could not find a easy way to do that without recreating the release template at the product line level.
Joshua Deixler
about 5 years ago
in Releases
2
Future consideration
Bulk Delete Phases to Release/ Change Phase Template of Releases
I would like to bulk delete the phases under releases. The current process of deleting phases is time consuming as we have to delete one phase at a time. It would be best to have bulk delete option for release. We have experienced a lot of difficu...
Guest
about 6 years ago
in Releases
2
Unlikely to implement
Release templates - ability to set default at parent line that is also then the default for all sub-products
The recent release template features have been great but as I have many sub-products within a parent-line, I have to go into each one to set the default release template. Please consider implementing a feature that allows you to force set the defa...
Dave Tucker
over 4 years ago
in Releases
0
Future consideration
Ability to add finish to finish dependencies in the Gantt chart
Some projects can only be completed once another task is completed, so to have a gantt chart that only allows for finish to start dependencies restricts the ability to add proper linkages and forecast
Ability to enter quarter dates for Internal date field
We currently have the ability to provide a quarter date to the external date field but not the internal date field. Having the ability to show a quarter date in both fields will help show on our roadmaps that we still need a committed date. With t...
Guest
over 4 years ago
in Releases
0
Future consideration