Project tracking: introduce feature-level project tracking, and reflect in release GANTT chart

Right now, a release consists of phases: definition, dev, QA, beta etc. And the release GANTT chart shows it nicely.

However, from a project management perspective, it would be great if we could track this at the feature-level, and show the feature level GANTT, similar to what MS Project does.

  • ADMIN RESPONSE
    Jan 27, 2015

    Features now have the concept of time.  You can display features on the Release -> Portfolio Gantt view and track feature due dates as well as dependencies.  

  • Attach files
  • Guest
    Reply
    |
    Dec 22, 2014

    100% Agree - We have had this request many time from our internal stakeholders, and it needs to represent changes that we make to our estimates for a feature directly back into the GANTT chart, which currently its not doing