We want the ability to better integrate our software and operational timelines is important to us a company. AHA! is our primary software development road mapping tool. We are a Microsoft "shop" and utilize the complete suite of tools for a 1000 employee company. This would be a great improvement for our operations to see the phases of the development cycle in our MS project.
Definitely wanted. Spoke with Microsoft regarding integrations for MS Project and they are looking to other vendors to provide the interfaces to their tools.
We haven't found the possibility in AHA! to level project ressources and manage issues while running out of ressource capacity like we were used to in MS Project. The dependencies between time scheduled features, master features and relating ressources is very difficult to handle in AHA!, also the presentation of these issues. Synchronization between AHA! und Ms Project both is strongly needed!!
Since Aha does not have a concept of baseline vs. actual. I also need to provide a WBS dictionary and this application does not do that, whereas it is easy to provide this in MS Project.
MS Project allows resource levelling which is very difficult to do in Aha! It would be great to have a VBA code example for MS Project that loads in the Aha! data and allows the due dates/work complete to be pushed back. Is this possible with the existing Aha! API?
I would like to allow my project manager to keep track of dates and deliverables through MS Project and those dates stay in sync with Aha!. Allowing the project manager to only have one place to work and not so many other places.
We are building requirements w/ cross functional teams (engineering, services, marketing, partners) that we need to include in releases. Currently, engineering is the only team utilizing while others are utilizing Microsoft Project to work their r...
Danielle Martinez
almost 3 years ago
in Integrations
0
Future consideration
We want the ability to better integrate our software and operational timelines is important to us a company. AHA! is our primary software development road mapping tool. We are a Microsoft "shop" and utilize the complete suite of tools for a 1000 employee company. This would be a great improvement for our operations to see the phases of the development cycle in our MS project.
At minimum need a basic integration to map a few fields.
I'd take this a level deeper as well, and look into linking MS Planner tasks to Aha To-Dos to better manage granular activities at feature/epic level.
Found someone who provides a connection - https://www.project-online.com/product/aha-integration-for-project-online/
Definitely wanted. Spoke with Microsoft regarding integrations for MS Project and they are looking to other vendors to provide the interfaces to their tools.
We haven't found the possibility in AHA! to level project ressources and manage issues while running out of ressource capacity like we were used to in MS Project. The dependencies between time scheduled features, master features and relating ressources is very difficult to handle in AHA!, also the presentation of these issues. Synchronization between AHA! und Ms Project both is strongly needed!!
Since Aha does not have a concept of baseline vs. actual. I also need to provide a WBS dictionary and this application does not do that, whereas it is easy to provide this in MS Project.
MS Project allows resource levelling which is very difficult to do in Aha! It would be great to have a VBA code example for MS Project that loads in the Aha! data and allows the due dates/work complete to be pushed back. Is this possible with the existing Aha! API?
I would like to allow my project manager to keep track of dates and deliverables through MS Project and those dates stay in sync with Aha!. Allowing the project manager to only have one place to work and not so many other places.
It would be very handy to be able to export plans as MS project files, and ideally have a similar means of importing MS project files back in.