Skip to Main Content

Share your product feedback

Status Shipped
Categories To-dos
Created by Guest
Created on Feb 16, 2016

My stakeholders would like to see the progress bar for a phase but our To-dos are defined within features that are defned under phases.

Hello.

We have several workstreams collaborating to complete phases of work. So what I do is I define one to many features under a phase. 

Each feature represents a workstream (I use the feature tag to define the workstream). I usually defne 1 to many To-Dos 'under' a feature. The drawback to defining To-Do's under features is that we lose the application of the Progress Bar for that phase.

I really think that my stakeholders would be over the top, if Aha! can propagate/automate the progress bar for the phase when the To-Dos are defined under Features. Please note that the Features defined are linked to the phase.

Thank you.

  • ADMIN RESPONSE
    Aug 7, 2019

    Great news! It is now possible to track progress on goals, initiatives, releases, release phases, master features, and features. The percent completed can be entered manually or automatically calculated based on related records and can be visualized using progress bars on roadmaps.

    Check out the blog post for more details.

  • Attach files
  • Max Cascone
    Reply
    |
    Feb 9, 2017

    Yes, yes, a thousand times yes. This functionality is already provided for Phases and To-Do's. Providing the same functionality for Features would be huge. 

    Request: provide the same progress visualization based on To-Do's that is provided in Phases, in Features.

  • Guest
    Reply
    |
    May 24, 2016

    I would love to see some additional roll-up to the release, not just progress on related feature to-dos. For example, it would be particularly helpful if the release phase reported summaries like the number of features and their requirements, and also indicated that there are feature dependency relationships with other features.