A common agile practice is to track progress by the burn up of completed things. I see there is already this kind of calculation for completed features. Need the same thinking to be applied to tracking initiative progress by calculating subordinate completed master features.
Thank you for your idea. As noted it is not possible to calculate initiative progress by master features completed. However you can calculate based on master feature progress. The reason for this is because master features are typically larger themes of work, where progress is tracked at a more granular level. Therefore tracking calculating progress based on current master feature progress would be more accurate.
Given the explanation above and current priorities, we are unlikely to add an option to calculate based on master features completed.