Dear aha,
in our scenario when AHA is synced with JIRA with time tracking attributes, we come into a problem with showing the complete work done on the feature when:
1. there is a time log in JIRA on epic (synced to feature)
2. there is a time log in JIRA on epic's stories, bugs, spikes (synced to requirements).
Right now it is impossible to configure the synchronization and time tracking abilities (up to my knowledge) in a way, that the feature would show one number of work done by making a sum of time spent from feature and requirement level.
This effectively blocks us from using reporting from aha that would show to our stakeholders the original estimate and work done so far.
Can you please think of ways how to overcome this issue within Aha?
Thanks for the tip, I will try it out.
Thanks for sharing this idea! We will continue to monitor feedback here.
This calculation is possible today for Enterprise + customers via custom worksheets fields (see the
work_done
field here).