Add Lead Time and Cycle Time lists and charts

Lead times (created to done) and cycle times (in progress to done) are the flow management tools used with a kanban practice. We mostly use these for Goal and Initiative records. Currently creating list report and export for charting in excel.

  • ADMIN RESPONSE
    May 13, 2022

    Thank you for your idea. This is currently possible using calculated columns. Within a list report you can create the calculated column to calculate the difference between the completion date and created date (or start date.) You can then switch the report type to a pivot or chart for additional visualization options.

    This support article provides more details on how to use calculated columns.




    Measure cycle and lead time in Aha! Develop

    Agile development teams can now measure cycle and lead time in Aha! Develop — so you can set delivery expectations with confidence.

    Try it now

  • Attach files
  • Jason Gillmore
    Reply
    |
    Mar 9, 2022

    However there is no way (to my knowledge as I have asked Aha! Support) to show TRENDING of lead time and cycle time over time. This is a health metric critical to lean agile / kanban. This is the use case they are probably exporting to Excel or another tool to produce, as I am doing.