What is the challenge? |
Currently, when using parallel planning the capacity report will look at the work item’s estimate and duration (start/end dates), and evenly spreads the estimate across the entire date range. So let’s say you have a feature with an estimate of 10 days and a duration of 5 months. The report would schedule 2days worth of work each month. It does not check if there is additional capacity and try to fill it/complete the work faster. |
What is the impact? |
You can end up with situations where you have available capacity |
Describe your idea |
A hybrid between sequential and parallel planning, where we spread estimates across the duration, but also fill capacity to 100% if capacity is available. |