Log work when importing completed records

My use case:

I have existing epics in progress I want to import from Jira and I want to show accurate progress towards these epics based on story points completed.


Here is the situation I am running:

  • Create an epic in Jira, and 2 child stories under that epic

  • Log story points on the stories and mark one story as Done

  • Then import the epic into Aha!, then import the child stories

  • I see the detailed estimate showing the correct sum on the epic, but no work is showing as complete from the one completed story.

I want to see this already completed work towards my epic show up as part of the progress calculation when calculating from remaining estimate.