Track progress on features before they are complete

It seems that the progress chart is only showing progress after a feature in a release is marked as "Complete". Is there a way based on daily "work Performed" and "Work Remaining" entries that I can incremental progress? Otherwise the burn-down re...
Guest about 10 years ago in Releases 1 Shipped

Ability to mark phases and milestones as completed (without creating to-dos)

For the phases, it would be very helpful for Program Management to be able to acknowledge that a phase has completed and allow for the establishment of a baseline like (estimated date) and actual date. That would include the planned release date t...
Suzanne Vaughan about 10 years ago in Releases 5 Shipped

Project tracking: introduce feature-level project tracking, and reflect in release GANTT chart

Right now, a release consists of phases: definition, dev, QA, beta etc. And the release GANTT chart shows it nicely. However, from a project management perspective, it would be great if we could track this at the feature-level, and show the featur...
Guest about 10 years ago in Releases 1 Shipped

Visualizing feature dependencies over releases

We have features that are done in incremental and iterative way over several releases. When there is a link between two features that are part of two different releases it should be visualized. In addition, there should be an notification, or aler...
Guest over 10 years ago in Releases 1 Shipped

Configure multiple release phases templates per product\product line

A product line often has several types of releases that may require different milestones. For example: Sprint releases with planning, development and release milestones released every 2 weeks Beta releases with planning, alpha, training, communica...
Guest over 10 years ago in Releases 0 Shipped

Capacity tracking for assignees

I have resources (assignees) that are assigned to features across multiple products and product lines. I'd like the capacity planning functionality to be able to track when I've over-committed them
Guest almost 11 years ago in Releases 4 Shipped